Date:

Time:

Statistics

Present:

14

Absent:

2

Total:

16

Team A (C 305)
Siddhesh Mhaparle (Mechanical Engineer)
1) Structure & Equipment Fabrication 08/10/25
2) L90 angle support Welding 09/10/25
3) L90 X 90 angle fit-up 4 Nos. 08/10/25
Team B (C 301)
DVSR Nikhil (Mechanical MT)
1) Civil work of cutout (2 Nos.) 09/10/25
2) To workout installation of Boiler feed pump, Tullu pump & Chiller 09/10/25
3) Pipe support fabrication 09/10/25
4) Installation of boiler exhaust pipe line, blind flange on D1 nozzle 09/10/25
Team C (7105)
Sumeet Dave (Process Engineer)
1) Inter connected spools labelling 09/10/25
2) Painting of Lines 09/10/25